X52 PSL2 ERW Steel Pipe in Malaysia

Sources: this site    Click:    Date: 2015-12-13 1:48:39

Order  Production Schedule

Our Order No.

20151101

Client's Order No.

ABE-02565376

Desription of Order

API 5L X52 PSL2 ERW Steel Pipe in  Malaysia (880 MT) 14" / 24"*SCH80

Process steps

From date

To date

Delivery Time

Proforma invoice signed

2015-10-01

2015-10-01

-

Down payment received date

2015-10-3

2015-10-3

-

Feed materials purchasing date

2015-10-4

2015-10-15

12days

Start production 

2015-10-16

2015-10-31

16days

Technical operation

2015-11-01

2015-11-4

4days

Pipe end, marking

2015-11-05

2015-11-07

3days

The third party inspection

2015-11-08

2015-11-10

3 days

Total

40 days