LSAW Steel Pipe in South Africa

Sources: this site    Click:    Date: 2015-11-3 0:38:41

Order  Production Schedule

Our Order No.

20151101

Client's Order No.

ABE-20151101

Desription of Order

st37 LSAW Steel Pipe (420 PCS) 32"*20

Process steps

From date

To date

Delivery Time

Proforma invoice signed

2015-10-1

2015-10-1

-

Down payment received date

2015-10-2

2015-10-3

2days

Feed materials purchasing date

2015-10-4

2015-10-7

4 days

Start production 

2015-10-8

2015-10-20

13 days

Technical operation

2015-10-21

2015-10-25

5 days

Pipe end, marking

2015-10-26

2015-10-27

2 days

The third party inspection

2015-10-28

2015-10-29

2 days

Total

29 days