Order Production Schedule | |||
Our Order No. | 20151010 | ||
Client's Order No. | ABE-14521365 | ||
Desription of Order | BS 1387 Galvanized Pipe in Panama (300 PCS) 42.2*2.65 | ||
Process steps | From date | To date | Delivery Time |
Proforma invoice signed | 2015-10-10 | 2015-10-10 | - |
Down payment received date | 2015-10-12 | 2015-10-12 | - |
Feed materials purchasing date | 2015-10-13 | 2015-10-18 | 7days |
Start production | 2015-10-19 | 2015-11-6 | 18 days |
Technical operation | 2015-11-7 | 2015-11-8 | 2days |
Pipe end, marking | 2015-11-9 | 2015-11-10 | 2 days |
The third party inspection | 2015-11-11 | 2015-11-12 | 2 days |
Total | 31 days |