BS 1387 Galvanized Pipe in Panama

Sources: this site    Click:    Date: 2015-11-16 1:8:13

Order  Production Schedule

Our Order No.

20151010

Client's Order No.

ABE-14521365

Desription of Order

BS 1387 Galvanized Pipe in Panama (300 PCS) 42.2*2.65

Process steps

From date

To date

Delivery Time

Proforma invoice signed

2015-10-10

2015-10-10

-

Down payment received date

2015-10-12

2015-10-12

-

Feed materials purchasing date

2015-10-13

2015-10-18

7days

Start production 

2015-10-19

2015-11-6

18 days

Technical operation

2015-11-7

2015-11-8

2days

Pipe end, marking

2015-11-9

2015-11-10

2 days

The third party inspection

2015-11-11

2015-11-12

2 days

Total

31 days