API 5L Q345B SMLS in Iran

Sources: this site    Click:    Date: 2015-12-13 1:47:9

Order  Production Schedule

Our Order No.

20150901

Client's Order No.

ABE-02415376

Desription of Order

API 5L Q345B SMLS in Iran(1690 MT) 21.3-406.4mm

Process steps

From date

To date

Delivery Time

Proforma invoice signed

2015-9-01

2015-9-01

-

Down payment received date

2015-9-3

2015-9-3

-

Feed materials purchasing date

2015-9-4

2015-9-25

22days

Start production 

2015-9-26

2015-10-31

36days

Technical operation

2015-11-01

2015-11-4

4days

Pipe end, marking

2015-11-05

2015-11-07

3days

The third party inspection

2015-11-08

2015-11-10

3 days

Total

68 days