API 5L Q345B SMLS in Iran
Sources: this site Click: Date: 2015-12-13 1:47:9
Order Production Schedule | |||
Our Order No. | 20150901 | ||
Client's Order No. | ABE-02415376 | ||
Desription of Order | API 5L Q345B SMLS in Iran(1690 MT) 21.3-406.4mm | ||
Process steps | From date | To date | Delivery Time |
Proforma invoice signed | 2015-9-01 | 2015-9-01 | - |
Down payment received date | 2015-9-3 | 2015-9-3 | - |
Feed materials purchasing date | 2015-9-4 | 2015-9-25 | 22days |
Start production | 2015-9-26 | 2015-10-31 | 36days |
Technical operation | 2015-11-01 | 2015-11-4 | 4days |
Pipe end, marking | 2015-11-05 | 2015-11-07 | 3days |
The third party inspection | 2015-11-08 | 2015-11-10 | 3 days |
Total | 68 days |